Umbata Falls Hydroelectric Development

- 2006 -

Location: Marathon, Ontario

Client: Umbata Falls Limited Partnership – Begetekong Power Corporation (Majority Owned by Ojibways of the Pic River First Nation), Innergex Group

Transmission Line Voltage: 115kV

Transmission Line Length: 22.6km

Structure Type: Single Pole w/ Stand-Off Insulators

# of Structures: N/A

Water Generation Capacity: 23MW

Services provided:

  • Right-Of-Way Clearing
  • Engineering
  • Procurement
  • Construction of Transmission Line
  • Right-Of-Way Restoration

Other Challenges:

  • 100% Off-road Construction
  • Highway 17 crossing
  • CP Rail Crossing
  • Hydro One Line Crossing